Ventilation systems were installed throughout the entire building. After the ventilation installation project was prepared by our company, its implementation was carried out accordingly. The systems listed above and the connected ventilation installations were completed. The project was completed within a total of 8 months.
Products Used
3 Air Handling Units
4 Cell-Type Exhaust Fans
1 Roof-Type Exhaust Fan
The hospital was constructed with a radiator-based heating system and an HVAC-based cooling and ventilation system. As a research and application hospital, it includes all necessary departments and units. The project consists of one 10-story block and five 4-story blocks. All operating rooms, intensive care units, and similar critical areas are conditioned using hygienic ventilation systems. The project was completed within a total of 3 years. Heating, cooling, ventilation, fire protection, plumbing, and automatic control systems were installed throughout the entire hospital.
Products Used
1 Air-Cooled Chiller Unit
30 Air Handling Units
5 Hygienic Air Handling Units
40 Steam Humidifiers
32 Cell-Type Exhaust Fans
11 Ducted Type Air Conditioners
24 VAV CAV Units
1 Water Tank (100 Tons)
1 Fire Booster Pump
1 Domestic Water Booster Pump
2 Boilers
6 Heating Circuit Plate Heat Exchangers
24 Heating and Cooling Circulation Pumps