We worked solely as the ventilation subcontractor for this project. The showroom was air-conditioned using an air handling unit, while all other areas were conditioned with fan coil systems. The project was carried out by our company on a partial material supply basis and was completed within 24 months.
The equipment listed below was installed by our company as part of the system. In addition to these units, all ventilation ductwork fabrication and installation works were carried out by our team. Furthermore, the exhaust chimney systems for the paint drying ovens were also designed and installed by our company.
Products Used
5 Air Handling Units
16 Cell-Type Exhaust Fans